Annual Absence Rates Project Time Formula

Learn how annual absence rates are used to estimate lost project hours, remaining capacity, person-days, and FTE capacity loss.

This calculation starts with the team’s planned annual project time and applies an expected absence rate. It helps project planners set a realistic capacity allowance before scheduling work or estimating staffing needs.

  • 100% Free
  • No Sign-Up Required
  • Private & Secure
  • Mobile Friendly

Available Annual Project Hours

Available project hours = Team size × Working days per employee × Project hours per day × (1 − Absence rate ÷ 100)

Where:

Calculate all planned project hours for the team, then reduce that total by the percentage of time expected to be lost to absence.

Variables Explained

VariableWhat It MeansUnit
teamSize - Team sizeNumber of people expected to contribute to the project.number
workingDaysPerEmployee - Working days per employee per yearPlanned annual working days after holidays and other planned non-working days, before absences are deducted.days
hoursPerDay - Project hours per working dayAverage productive project hours planned for each person on a working day.hours
absenceRate - Annual absence rateExpected percentage of planned work time that will be unavailable because of absence.percent

Step-by-Step Calculation

1

Calculate planned annual project hours

This is the team’s total annual project capacity before allowing for absence.

plannedAnnualHours = teamSize * workingDaysPerEmployee * hoursPerDay

2

Convert the absence percentage to a decimal

A percentage must be divided by 100 before it is applied to project hours.

absenceDecimal = absenceRate / 100

3

Calculate project hours lost to absence

This estimates how many planned project hours are unavailable during the year.

absenceHours = plannedAnnualHours * absenceDecimal

4

Calculate available project hours

Subtract estimated lost hours from planned annual hours to find the remaining capacity.

availableProjectHours = plannedAnnualHours - absenceHours

5

Express lost time in person-days and FTE

Lost hours can be converted into person-days, while FTE loss shows the average team capacity represented by the absence allowance.

absenceDays = absenceHours / hoursPerDay; fteCapacityLost = teamSize * absenceDecimal

Example: 10-person team with 5% annual absence

Team size10 employees
Working days per employee220 days per year
Project hours per day7.5 hours
Annual absence rate5%
1

Find planned annual hours

10 × 220 × 7.5

16,500 hours

2

Calculate lost absence hours

16,500 × 5 ÷ 100

825 hours

3

Calculate available project hours

16,500 − 825

15,675 hours

4

Convert lost hours to person-days

825 ÷ 7.5

110 person-days

5

Calculate FTE capacity lost

10 × 5 ÷ 100

0.50 FTE

Final Result

The team is estimated to lose 825 project hours, or 110 person-days, and retain 15,675 annual project hours.

Try the Calculator →

Assumptions

  • The absence rate applies evenly across the team over the full year.
  • Working days are entered after planned annual leave, public holidays, and other known non-working days have been removed.
  • Each employee is assumed to contribute the same number of project hours per working day.
  • Project hours lost to absence are assumed not to be replaced by overtime, temporary cover, or reprioritised work.

Limitations

  • !Actual absences may be clustered rather than spread evenly, which can create delivery delays beyond the annual hours total.
  • !Individual schedules, roles, part-time arrangements, and productivity levels may differ across the team.
  • !The estimate does not include turnover, recruitment gaps, training, meetings, or changes in project scope.
  • !A capacity allowance does not predict the timing or cause of individual absences.

Common Mistakes to Avoid

1

Including annual leave in both the working-days input and the absence rate.

2

Using contracted daily hours instead of the productive project hours realistically available each day.

3

Entering 5 as 0.05 when the calculator expects an absence percentage of 5%.

4

Treating the FTE result as a specific vacant role rather than an annual average capacity equivalent.

5

Assuming remaining annual hours are automatically available at the exact times the project needs them.

Related Formulas

Frequently Asked Questions

How do you calculate annual project hours lost to absence?

Multiply planned annual project hours by the annual absence rate divided by 100. Planned annual hours equal team size multiplied by working days per employee and project hours per day.

How is available project time calculated after absence?

Subtract estimated absence hours from planned annual project hours. The same result can be calculated by multiplying planned hours by one minus the absence rate as a decimal.

What does 0.5 FTE capacity lost mean?

It means the annual absence allowance is equal to half of one full-time employee’s annual capacity on average. It does not mean one person will be absent for half the year.

Should holidays be included in the absence rate?

Usually, planned holidays and public holidays should be removed when entering working days. The absence rate can then represent unplanned or separately tracked absences.

Why are absence days shown as person-days?

Person-days convert lost hours into whole or partial workdays using the project hours entered per day. They describe total team time, not necessarily consecutive calendar days.